In order to determine the critical path, it is first essential to calculate forward pass (earliest start, earliest finish), backward pass (latest start, latest finish) and slack or float time for each activity. Table 1 represented below depicts the result of the calculation forward pass, backward pass and slack/float of the listed activities. It can be observed from the table below that the estimated project completion time has been calculated as 280 days